IPS provided the project and construction management role for the CSBP Ammonium Nitrate 2 Expansion Project including overall fabrication works for the Stainless Steel Process Vessels and Tanks.
IPS maintained a full time fabrication management representative to interface with the supplier regarding shop manning levels, job supervision management, schedule/cost control and reporting, QA/QC and MDR compilation and finalisation.
The scope of the project comprised:
Project Facts | |
Location | Kwinana, WA |
Client | CSBP Limited |
IPS Role | Fabrication Management |
In April of 2010 IPS was engaged by Moly Metals